Planning and monitoring communication between construction project participants
 
More details
Hide details
1
MSc. Eng., Cracow University of Technology, Faculty of Civil Engineering, ul. Warszawska 24, 31-155 Cracow, Poland
 
2
PhD. Eng., Cracow University of Technology, Faculty of Civil Engineering, ul. Warszawska 24, 31-155 Cracow, Poland
 
3
Prof. PhD. Eng., Cracow University of Technology, Faculty of Civil Engineering, ul. Warszawska 24, 31-155 Cracow, Poland
 
 
Submission date: 2020-11-11
 
 
Acceptance date: 2020-11-17
 
 
Publication date: 2021-06-24
 
 
Archives of Civil Engineering 2021;67(2):455-473
 
KEYWORDS
TOPICS
ABSTRACT
In the literature, researchers present construction projects as temporary self-organising coalition networks, composed of specialist entities that work towards set goals. The number of parties involved in the various processes during construction causes communications relations to be exceedingly complex and to change. The environment of a construction project is dynamic and complex, and self-organising communication networks are sensitive to institutional and social change. It becomes necessary to identify situations rooted in both insufficient communication during the carrying out of a project and its excess, which generates unnecessary cost. Effective control of information flow within self-organising communication networks through its planning and monitoring by project management can contribute to achieving project goals. This paper presents a proposal of an optimisation approach (in terms of minimising communication costs) to information flow planning that accounts for various constraints, on the example of a real-world case of building a housing complex in Poland.
eISSN:2300-3103
ISSN:1230-2945
Journals System - logo
Scroll to top